DATA
Facility use | Label printing factory |
---|---|
Summary | Total floor space: approx. 6,000㎡ |
Location | Ichinomiya City, Aichi Prefecture |
Services we provided
The following services were provided as engineering consulting
- 1.URB (User Requirements Brief) development support
- 2.Conceptual design
- 3.Preparation of construction drawings
- 4.Support services for determining the construction contractor
- 5.Detailed design management
- 6.Construction supervision
Project phase
-
3 months
Prepare URB
-
4 months
Prepare Conceptual Design/Quotation form
-
3 months
Construction company quotation inquiry stage
-
16 months
Detailed design /construction phase
Our contributions to the project
-
CM Plus prepared a URB (User Requirements Brief) for the production volume of the product to be manufactured (pharmaceutical labels), the utility conditions of the production facility, and the requirements for the facility and equipment.
-
In the conceptual design phase, CM Plus worked with the client on a land use plan that took into account future concepts in the site utilization plan, and studied the layout plan (first phase plan).
In order to realize one of the project concepts, “meeting global quality requirements” we adopted a concept that conforms to GMP-compliant facilities.
Specifically, we aimed for the quality of a pharmaceutical plant, with clear and step-by-step area separation, air conditioning, insect control, and a product transfer system/plan and cross-sectional plan that links the automated warehouse and production system. -
In order to get the project right, we provided a rough estimate and assisted the client in developing a budget.
-
At the construction inquiry stage, CM Plus prepared specifications and books for quotation inquiries with clear specifications. This made it possible to conduct quotations from multiple construction companies and evaluate their quotations fairly.
In selecting a construction company, we evaluated the cost and technical evaluation using a comparison table, and conducted interviews with each company together with the client to select the best construction company. -
During the construction phase, we attended regular meetings held at the site and contributed to ensuring good construction quality by supervising construction progress, checking construction quality, confirming changes, and assessing additional construction costs.
-
After the operation started, we have been informed that many end-user pharmaceutical manufacturers have commented that the plant complies with GMP in their manufacturing process (labeling) inspections and plant inspections, and we believe that the plant meets the needs of our customers.
Client Testimonials
Other Projects
-
Pharmaceuticals and Medical Devices Large-scale medical device manufacturing facility equipped with the latest logistics system Terumo Yamaguchi Corporation
-
Pharmaceuticals and Medical Devices Manufacturing facility for bio-based Class IV implantable medical devices CoreTissue BioEngineering Inc.
-
Pharmaceuticals and Medical Devices/Medium-Molecule API Cost reduction through separate sub-contracting Jitsubo CO., LTD.
-
Cosmetics “Show” cosmetics factory Toyo Beauty Co., Ltd.
-
Data Centers System module type data center
Realizing short construction period and low cost Internet Initiative Japan Inc. -
Pharmaceuticals and Medical Devices Large-scale medical device manufacturing facility that considers people, the community, safety, and the environment. Terumo Vietnam Co., Ltd.
-
Food/Flavor・Fragrance Smooth project execution between Asia headquarter and Japan head office Takasago International Singapore Pte. Ltd.
-
Pharmaceuticals and Medical Devices Production line reinforcement for pharmaceutical manufacturing factory Medreich Limited